How the budget is check when we assign PM Order to WBS?Does the budget check at WBS element?
来源:学生作业帮助网 编辑:作业帮 时间:2024/10/02 14:27:30
How the budget is check when we assign PM Order to WBS?Does the budget check at WBS element?
How the budget is check when we assign PM Order to WBS?Does the budget check at WBS element?
How the budget is check when we assign PM Order to WBS?Does the budget check at WBS element?
Elle, the availability control (budget check) occurs at the WBS element. When a budget value is present at a WBS, the WBS becomes a controlling element for the budget check, i.e. if you only budget at the level 1, the level 1 controls the entire structure. If you budget at the level 2's, each is a controlling element. Any linked object, such as a PM order then becomes subject to the budget check.Hope this helps!Bill 查看原帖>>